Poster/Video/Timeline: Work

TEAM PRESENTATION

Poster/Video/Timeline: Text
Poster/Video/Timeline: Video
Capstone picture.PNG
Poster/Video/Timeline: Image

KEY EVENTS

The Wall of Ideas

PROJECT BEGINNING

October 11th, 2020

Throughout the timeframe of September and beginning of October, we had to go to the white board. This was our initial brainstorming phase for ideas. When we decided upon a project with Levi Zaleski's co-op company. The Wire Tracker.

PARTS DELAYMENT

October-November

During the pandemic this last year, we did not anticipate how much parts delay would effect us until we were in it. Key components were trickling in, pushing us behind schedule in the first semester.

Image by ray sangga kusuma
thumbnail_IMG_4480_edited.jpg

CODE DEVELOPMENT/ SMALL TESTING

November - December

During the November/December timeframe, we were developing our code and working with what parts we were able to obtain. The software development was the most time consuming portion of the project.

INITIAL CONSTRUCTION

January 20, 2021

Once back from winter break, we were able to construction our prototype. All parts were in. During this time we were also conducting small scale testing.

Initial.jpg
Levi.jpg

FIRST FULL SCALE TEST

March 3rd, 2021

Our device was ready for the field test, we met a Duke Energy team in Oxford,OH to test our device out on the full scale rig.

FINAL FULL SCALE

March 22nd, 2021

Our final full scale test occurred on March 22nd in Oakley, OH. We were able to track over 800 feet of cable that was pulled accurately.

MicrosoftTeams-image (3).png
Poster/Video/Timeline: Past Events